Dear Service Engineer, It is well known fact that instrumentation which is well taken care of will out perform and out last than which is not. The Mindray BS-200 Automatic Chemistry Analyzer is no exception to this rule. Chemistry systems that are well taken care of by their users and service personnel will have many fewer problems than those which are not. Fewer problems mean fewer service calls, and happier customers. The preventive maintenance (PM) manual is offered as a standard guide to follow. You will find that, depending on the quality of care which an instrument receives, 12 months preventive maintenance visits will require varying degrees of thoroughness. The important point here is that the reliability of the Mindray BS-200 is somewhat dependant on the quality and quantity of attention it receives during its 12 months preventive maintenance visit. The service engineer has a substantial amount of influence on the call rate of each system. Taking a little extra time to educate users as to the proper way of caring for an instrument will, on most cases, increase the instruments reliability, and the customer’s satisfaction. This manual is intended for use only by Service Engineers who are trained by Mindray and do not replace or reduce the operator maintenance recommended in the BS-200 Operator’s Manual. Unauthorized use of these procedures can damage the analyzer and void the warranty of contract. The PM kit contains the parts needed for the preventive maintenance. Other parts can be replaced at additional cost. If you have any questions or suggestions, please email us at

Sincerely, Mindray Service Team

2

[email protected]

Catalog 1

Part list of Preventive Maintenance Kit .................................................................... 3

2

Replacement ................................................................................................................ 5

3

2.1

Replacing Halogen Lamp(50W) ........................................................................ 5

2.2

Replacing Sample Probe And Washer&Uncloging Probe............................. 7

2.3

Replacing Syringe Plunger ............................................................................... 11

2.4

Replacing Mixing Bar and Retaining Nut ....................................................... 13

2.5

Replacing Filter Assembly ................................................................................ 14

2.6

Replacing Check Valve ..................................................................................... 16

Chemistry Maintenance schedule………………………………………….18

3

[email protected]

1 Part list of Preventive Maintenance Kit FRU

801-BA20-00186-00

Definition

BS-200 Preventive Maintenance Kit

Part No

Name

BA30-10-06365

Halogen Lamp(50W)

2

BA40-30-61525

Sample probe

1

0040-10-32307

Washer for Probe

4

115-003182-00

Probe Unclog Tool

1

0000-10-10916

Acupuncture Needle

10

082-000731-00

Syringe Plunger (500ul, zero dead volume)

0040-10-32303

Washer for Syringe

BA31-20-41651 +

Mixing Bar + Retaining

BA30-20-06774 BA31-30-56750 M6Y-020003---

Nut Filter Assembly (2 Pcs, 1pkg) Check Valve

Time: The average time to complete this preventive maintenance procedure is 4 hours, it depends on the on-site engineer experience and analyzer condition.

4

Qty

1 2 1 1 4

[email protected]

2 Replacement 2.1 Replacing Halogen Lamp(50W) 2.1.1 Part Number BA30-10-06365

Halogen Lamp(50W)

2.1.2 Purpose For sufficient lamp intensity and reliable testing results 2.1.3 Interval Every 6 months Every 1000 hours When the machine reminds you to do so 2.1.4 Procedures 2.1.4.1 Place the Main Power to OFF. Wait at least 15 minutes for the lamp and its housing to cool down 2.1.4.2 Unscrew the retaining screws on the back cover of the analyzing unit and remove the back cover. You can see the following box in the left lower part of the cabinet, where the lamp housing locates

2.1.4.3 Unplug the connector of the wire.

5



2.1.4.5 Unscrew the screws on the back of the lamp housing with a hex wrench and remove the radiator from the housing backwardly.

2.1.4.6 Pinch the base of the lamp with one hand and press the lever on the left of the base and remove the lamp.

2.1.4.7 Pinch the new lamp by its base and insert the lamp pins into the mounting holes. 2.1.4.8 Install the radiator back to the home position and tighten the screws. 2.1.4.9 Install the cover back to the box and tighten the screws. 2.1.4.10 Close the back cover of the analyzing unit and tighten the screws.

2.1.5 Verification After new lamp is installed, run starting procedure, enter the software interface and check the background of the 8 wavelengths at the “Maintenance” interface. If the background

is

lower

than

65535, 6

the

replacement

is

successful.

[email protected]

2.2 Replacing

Sample

Probe

And

Washer&

Uncloging Probe 2.2.1 Part Number BA40-30-61525

Sample Probe

0040-10-32307

Washer for Probe

0000-10-10916

Acupuncture Needle

115-003182-00

Probe Unclog Tool

2.2.2

Purpose

If the probe is bent or damaged, it must be replaced immediately. Follow the procedure given below to replace the damaged or bent probe.

2.2.3

Interval

Every year

2.2.4 Procedures 2.2.4.1 Place the Power to OFF. 2.2.4.2 Remove the sample/reagent disk. 2.2.4.3 Pull the probe arm to the highest point by hand. Rotate the probe arm to move the probe to a position above the sample/reagent compartment and convenient to operate. NOTE:If the probe is clogged we chould try to use the Acupuncture Needle to unclog the probe. Use a needle to unclog the probe from the tip.

7



2.2.4.5 Hold the probe’ s fluid connector with one hand and the tubing connector with the other. Rotate the tubing connector counter-clockwise until it disconnects from the probe. Remove the tubing from the probe. You will see a small gasket inside the tubing connector which is removed from the probe. Exercise caution and make sure the gasket is always inside the tubing connector. If the gasket falls off, store it in a clean place 2.2.4.6 Press the circuit board with one hand and disconnect the probe’s circuit connector from the board with the other hand. Exercise caution when disconnecting the connector. Excessive force may damage the connector and/or the circuit board.

2.2.4.7 Use a slotted head screwdriver to remove the retaining screw on the probe and take out the spring. Store the removed probe in a safe place where it will neither endanger people working around the area nor be damaged. Exercise caution when pulling the probe away from the arm

2.2.4.8 Slowly pull the probe away from the probe arm. Exercise caution so that the gasket inside the probe does not drop out and if it does, store it in a clean place for later installation. When the probe is clogged, the fluid flow will become abnormal. Follow the steps given below to remove, unclog and install the probe.

2.2-1 How to use unclogging tool 2.2-1.1

Purpose

To keep the normal fluid flow

2.2-1.2

Interval

When the probe is clogged

2.2-1.3

Procedures 8

[email protected]

2.2-1.3.1.Place a container like beaker below the sample probe. 2.2-1.3.2.Connect the unclogging device to the tubing connector. 2.2-1.3.3.Use a single-use syringe to aspirate 3ml CD80 wash solution, remove the needle and connect the syringe to the other end of the unclogging device. 2.2-1.3.4.Push the syringe plunger slowly until there comes liquid out of the sample probe tip. If no liquid comes out of the sample probe tip, insert a needle into the sample probe tip and push the syringe plunger.

2.2-1.3.5.Leave the sample probe soaked with wash solution for about 10 minutes. Push and pull the syringe plunger for several times until liquid comes out of the probe tip evenly. 2.2-1.3.6.Use the syringe to aspirate deionized water and rinse the sample probe for at least 3 times. 2.2-1.3.7.Remove the unclogging device and the syringe, and then connect the tubing connector. 2.2-1.3.8.Remove the container.

2.2-1 How to replace the washer

2.2-2.1

Purpose

To keep the sealingness of the fluidic path and sampling precision well

2.2-2.2

Interval

If you remove and install the probe for about 2-3 times or it leaks between the probe’s fluid connector and the tubing connector, you should replace the washer with a new one. 9

[email protected]

2.2-2.3

Procedures

2.2-2.3.1 Follow the steps from 2.2.4.1-2.2.4.8 to remove the probe. You will see a small gasket inside the tubing connector which is removed from the probe.

2.2-2.3.2 Remove the old washer with tweezers and put a new one inside the probe. Dispose the old one in proper way.

The next step is installing the probe 2.2.4.9 Insert the probe back into the hole on probe arm, and align the hole on probe 2.2.4.10 plate to the rotor inside the arm. 2.2.4.11 Sleeve the spring on the rotor and screw the retaining screws to secure. 2.2.4.12 Pinch the probe by the part near the probe arm. Gently push the probe 2.2.4.13 upward and then release the probe to see if the spring can move freely. If yes, proceed to the next step. If not, check for errors and try again after removing the errors. 2.2.4.14 Connect the probe’ s circuit connector back to the circuit board

2.2.4.15 Ensure the gasket is inside the probe

2.2.4.16 Exercise caution when connecting the probe. Excessive force may bend the probe. Screw (clockwise) the probe’ s fluid connector back to the tubing connector.

2.2.4.17 Add deionized water to a clean cup. Immerse the probe tip into the water by about 3mm and the LED on the circuit board will be lighted. Take the probe tip out of water, and the LED will be off. If the test succeeds, proceed to the next step.

2.2.4.18 Check the marks inside the probe arm cover to see the orientation of the cover. Install the cover back to the probe arm.The marks inside the probe arm cover are shown in the figure below.

10

[email protected]

2.2.4.19 Pull the probe arm to its highest point and rotate it to move the probe to a position above the wash well. 2.2.4.20 Load the sample/reagent disk.

2.2.5 Verification Run the machine if no leakage around the connector,the replacement is OK.

2.3 Replacing Syringe Plunger 2.3.1 Part Number 082-000731-00

Syringe Plunger (500ul, zero dead volume)

0040-10-32303

Washer for Syringe

2.3.2 Purpose For reliable aspiration 2.3.3 Interval Every year Every 100000 movements 2.3.4 Procedures 2.3.4.1 Place the Power to OFF

2.3.4.2 Unscrew the screws on the syringe cover and remove the cover. The structure of the syringe is as shown in the figure below.

11

[email protected]

2.3.4.3 Prepare a new plunger assembly (shown in the figure below) and soak the plunger tip in deionized water to eliminate bubbles

2.3.4.4 Unscrew (counter-clockwise) the lower retaining screw. 2.3.4.5 Unscrew (counter-clockwise) the four retaining screws, remove the screws and space bars, and remove the syringe from the holder.

2.3.4.6 Grab the Tee with one hand and the syringe connector with the other hand and unscrew (counter-clockwise) the syringe. Exercise caution so that the gasket on the syringe does not drop out and if it does, store it in a clean place for later installation.

2.3.4.7 Unscrew (counter-clockwise) the plunger guide cap and pinch the plunger button to gently pull the plunger assembly from the syringe.

2.3.4.8 Pinch the new plunger assembly by the plunger button and carefully insert the plunger tip into the syringe and push it all the way to the end. Screw (clockwise) the plunger guide cap until secure

2.3.4.9 Immerse the syringe connector into deionized water. Pinch the plunger button, pull it to aspirate half syringe of deionized water and then push it to expel the deionized water and the air from the syringe. 12



2.3.4.11 Place the syringe on the holder. Install space bars and fix retaining screws. 2.3.4.12 Screw (clockwise) the lower retaining screw until secure. 2.3.4.13 Place the Power back to ON.

2.3.5 Verification Enter the Alignment screen of the operating software and set the Vol. (R. Syringe) to 450ul. Click R. Syringe Aspirate. After the syringe finishes the motion, click R. Syringe Dispense. You may repeat this action several times. If there are not bubbles observed during the process and the alignment is correct,everyting is ok.

2.4 Replacing Mixing Bar and Retaining Nut 2.4.1 Part Number BA31-20-41651, BA30-20-06774

Mixing Bar, Retaining Nut

2.4.2 Purpose For reliable testing results 2.4.3 Interval Every year 2.4.4 Procedures 2.4.4.1 Place the Power to OFF 2.4.4.2 Gently pull the bar arm to its highest point and move the bar to a position convenient to operate.

2.4.4.3 Pinch the bar by the knurled part with one hand and unscrew (counter-clockwise) the retaining nut with the other hand until the mixing bar looses. Pull the bar downward to remove it and remove the nut.

13

[email protected]

2.4.4.4 Align the new mixing bar to the bigger hole end of the retaining nut and gently screw it into the nut until the end of the bar is in line with the smaller hole end of the nut.

2.4.4.5 Pinch the mixing bar by the knurled part and align the hole of the nut to the axis on the bar arm, then push the bar upward in the direction of the axis until it can’t proceed. Tighten the nut by screwing clockwise with the other hand.

2.4.4.6 Ensure the bar is all the way pushed to the end. 2.4.5 Verification After replacing the bar, visually check whether the bar is vertical to the bar arm. If not, remove the bar and re-install it. If yes, proceed to the next step. 7 Pull the bar arm slightly and move the bar to a position above its wash well.

2.5 Replacing Filter Assembly 2.5.1 Part Number BA31-30-56750

Filter Assembly (2 Pcs, 1pkg)

2.5.2 Purpose Keep reliable testing results 2.5.3 Interval 14

[email protected]

Every 6 months 2.5.4 Procedures 2.5.4.1 Remove cap assembly from the DI water tank and place it on a clean desktop. Carefully remove the filter assembly from the cap assembly.

2.5.4.2 Inject water into the new filter assembly through the big adapter by using the syringe. When water wells up from the small adapter, the injection is completed. Purpose: increase the weight of the filter assembly to make it sink to the bottom of the water tank.

2.5.4.3 Connect the new filter assembly to the tubes of the cap assembly.

2.5.5.4 Expel air from the filter assemby 15



2.5.5 Verification Check for large amount of buubles in the outlet tube. If yes, continue the resetting process; if not, the air expelling is completed. The installation is completed.

2.6 Replacing Check Valve 2.6.1 Part Number M6Y-020003---

Check Vavle

2.6.2 Purpose To keep the sealingness of the fluidic path and unobstructed flow

2.6.3 Interval Every 6 months 2.6.4 Procedures 2.6.4.1 Remove the rear panel and find the Check Vavle.

16

[email protected]

Check Vavle 2.6.4.2 Replace the Check Vavles with the new ones.

2.6.5 Verification Run our analyzer and check if the liquid is weeping;If not,the replacement is OK.

17

[email protected]

3.

Chemistry Maintenance schedule BS-200 Maintenance Schedule

DI water tank

N/A

N/A

I

C

C

C

C

BS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.

Waste tank

N/A

N/A

I

C

C

C

C

BS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.

Inlet tubing of Cap assembly of DI Water Tank

N/A

N/A

I

I

I

I

I

BS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.

Outlet tubing of Cap assembly of Waste Tank

N/A

N/A

I

I

I

I

I

BS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.

Reagent/Sample disk

N/A

N/A

N

C

C

C

C

BS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.

Wash Wells of probe and mixing bar

N/A

N/A

N

C

C

C

C

BS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.

Dust Proof Net

N/A

N/A

N

N

C

C

C

BS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.

Sample/Reagent Bar Code Reader Windows

N/A

N/A

N

C

C

C

C

N

Cleaning Panels of Analyzing Unit

N/A

N/A

N

C

C

C

C

BS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.

Clean the Rotor of Reagent/Sample Probe/Mixer Drive Assembly

N/A

N/A

N

N

C

C

C

Wipe the rotor with clean gauze.

ISE daily cleaning

N/A

N/A

P

P

P

P

P

N

ISE pump calibration

N/A

N/A

P

P

P

P

P

N

I

I

I

I

I

N

ITEM

Related Part

Qty

12 MO NT

We ek ly Mo nth ly 6M on ths

WHICHEVER COMES FIRST

By Customer

EVERY

By Engineer

HS

C: Clean, R: Replace, A: Adjust, L: Lubricate, P: Perform, N: No action needed

Da il y

I: Inspect. Clean, Adjust or Replace if necessary.

ISE Na electrode

N/A

N/A

10,000 tests or 6 months

ISE K electrode

N/A

N/A

10,000 tests or 6 months

I

I

I

I

I

N

ISE Cl electrode

N/A

N/A

10,000 tests or 6 months

I

I

I

I

I

N

ISE Li electrode

N/A

N/A

3,000 tests or 6 months

I

I

I

I

I

N

ISE Ref electrode

N/A

N/A

10,000 tests or 6 months

I

I

I

I

I

N

Lamp

BA30-10-06365

Halogen Lamp(50W)

2

1,000 hours

N

N

I

R

R

Reagent/Sample probe

BA40-30-61525

Sample probe

1

I

C

C

C

R

Probe washer

0040-10-32307

Washer for Probe

4

I

C

C

C

R

Probe unclog tool

115-003182-00

Probe Unclog Tool

1

N

N

P

P

P

Acupuncture Needle

0000-10-10916

Acupuncture Needle

10

N

N

P

P

P

Syringe Plunger (500ul, zero dead volume)

082-000731-00

Syringe Plunger (500ul, zero dead volume)

1

I

I

I

I

R

Washer for Syringe

2

I

C

C

C

R

Mixing Bar + Retaining Nut

1

I

C

C

C

R

Syringe washer Mixing Bar + Retaining Nut

0040-10-32303 BA31-20-41651 + BA30-20-06774

100,000 movements

DI water filter assembly

BA31-30-56750

Filter Assembly (2 Pcs, 1pkg)

1

N

N

N

R

R

Check Valve

M6Y-020003---

Check Valve

4

N

N

N

R

R

18

Reference

BS-200 Chemistry Analyzer Preventive Maintenance ManualGlobal Technical Support Department For Bio-ChemistryDear Service Engineer, It is well known fact that instrumentation which is well taken care of will out perform and out last than which is not. The Mindray BS-200 Automatic Chemistry Analyzer is no exception to this rule. Chemistry systems that are well taken care of by their users and service personnel will have many fewer problems than those which are not. Fewer problems mean fewer service calls, and happier customers. The preventive maintenance (PM) manual is offered as a standard guide to follow. You will find that, depending on the quality of care which an instrument receives, 12 months preventive maintenance visits will require varying degrees of thoroughness. The important point here is that the reliability of the Mindray BS-200 is somewhat dependant on the quality and quantity of attention it receives during its 12 months preventive maintenance visit. The service engineer has a substantial amount of influence on the call rate of each system. Taking a little extra time to educate users as to the proper way of caring for an instrument will, on most cases, increase the instruments reliability, and the customer’s satisfaction. This manual is intended for use only by Service Engineers who are trained by Mindray and do not replace or reduce the operator maintenance recommended in the BS-200 Operator’s Manual. Unauthorized use of these procedures can damage the analyzer and void the warranty of contract. The PM kit contains the parts needed for the preventive maintenance. Other parts can be replaced at additional cost. If you have any questions or suggestions, please email us at [email protected] Sincerely, Mindray Service TeamCatalog 1Part list of Preventive Maintenance Kit .................................................................... 3Replacement ................................................................................................................ 52.1Replacing Halogen Lamp(50W) ........................................................................ 52.2Replacing Sample Probe And Washer&Uncloging Probe............................. 72.3Replacing Syringe Plunger ............................................................................... 112.4Replacing Mixing Bar and Retaining Nut ....................................................... 132.5Replacing Filter Assembly ................................................................................ 142.6Replacing Check Valve ..................................................................................... 16Chemistry Maintenance schedule………………………………………….181 Part list of Preventive Maintenance Kit FRU801-BA20-00186-00DefinitionBS-200 Preventive Maintenance KitPart NoNameBA30-10-06365Halogen Lamp(50W)BA40-30-61525Sample probe0040-10-32307Washer for Probe115-003182-00Probe Unclog Tool0000-10-10916Acupuncture Needle10082-000731-00Syringe Plunger (500ul, zero dead volume)0040-10-32303Washer for SyringeBA31-20-41651 +Mixing Bar + RetainingBA30-20-06774 BA31-30-56750 M6Y-020003---Nut Filter Assembly (2 Pcs, 1pkg) Check ValveTime: The average time to complete this preventive maintenance procedure is 4 hours, it depends on the on-site engineer experience and analyzer condition.Qty1 2 1 1 42 Replacement 2.1 Replacing Halogen Lamp(50W) 2.1.1 Part Number BA30-10-06365Halogen Lamp(50W)2.1.2 Purpose For sufficient lamp intensity and reliable testing results 2.1.3 Interval Every 6 months Every 1000 hours When the machine reminds you to do so 2.1.4 Procedures 2.1.4.1 Place the Main Power to OFF. Wait at least 15 minutes for the lamp and its housing to cool down 2.1.4.2 Unscrew the retaining screws on the back cover of the analyzing unit and remove the back cover. You can see the following box in the left lower part of the cabinet, where the lamp housing locates2.1.4.3 Unplug the connector of the wire. [email protected] Unscrew the screws on the box with a hex wrench and remove the cover 2.1.4.4 (together with the fan) backwardly.2.1.4.5 Unscrew the screws on the back of the lamp housing with a hex wrench and remove the radiator from the housing backwardly.2.1.4.6 Pinch the base of the lamp with one hand and press the lever on the left of the base and remove the lamp.2.1.4.7 Pinch the new lamp by its base and insert the lamp pins into the mounting holes. 2.1.4.8 Install the radiator back to the home position and tighten the screws. 2.1.4.9 Install the cover back to the box and tighten the screws. 2.1.4.10 Close the back cover of the analyzing unit and tighten the screws.2.1.5 Verification After new lamp is installed, run starting procedure, enter the software interface and check the background of the 8 wavelengths at the “Maintenance” interface. If the backgroundislowerthan65535, 6thereplacementissuccessful.2.2 ReplacingSampleProbeAndWasher&Uncloging Probe 2.2.1 Part Number BA40-30-61525Sample Probe0040-10-32307Washer for Probe0000-10-10916Acupuncture Needle115-003182-00Probe Unclog Tool2.2.2PurposeIf the probe is bent or damaged, it must be replaced immediately. Follow the procedure given below to replace the damaged or bent probe.2.2.3IntervalEvery year2.2.4 Procedures 2.2.4.1 Place the Power to OFF. 2.2.4.2 Remove the sample/reagent disk. 2.2.4.3 Pull the probe arm to the highest point by hand. Rotate the probe arm to move the probe to a position above the sample/reagent compartment and convenient to operate. NOTE:If the probe is clogged we chould try to use the Acupuncture Needle to unclog the probe. Use a needle to unclog the probe from the tip. [email protected] 2.2.4.4 Grab the lower part of the arm cover with two hands and pull them slightly outwards and remove the cover upward from the arm base. After you remove the cover, the inside structure of the probe arm is as shown in the figure below.2.2.4.5 Hold the probe’ s fluid connector with one hand and the tubing connector with the other. Rotate the tubing connector counter-clockwise until it disconnects from the probe. Remove the tubing from the probe. You will see a small gasket inside the tubing connector which is removed from the probe. Exercise caution and make sure the gasket is always inside the tubing connector. If the gasket falls off, store it in a clean place 2.2.4.6 Press the circuit board with one hand and disconnect the probe’s circuit connector from the board with the other hand. Exercise caution when disconnecting the connector. Excessive force may damage the connector and/or the circuit board.2.2.4.7 Use a slotted head screwdriver to remove the retaining screw on the probe and take out the spring. Store the removed probe in a safe place where it will neither endanger people working around the area nor be damaged. Exercise caution when pulling the probe away from the arm2.2.4.8 Slowly pull the probe away from the probe arm. Exercise caution so that the gasket inside the probe does not drop out and if it does, store it in a clean place for later installation. When the probe is clogged, the fluid flow will become abnormal. Follow the steps given below to remove, unclog and install the probe.2.2-1 How to use unclogging tool 2.2-1.1PurposeTo keep the normal fluid flow2.2-1.2IntervalWhen the probe is clogged2.2-1.3Procedures 82.2-1.3.1.Place a container like beaker below the sample probe. 2.2-1.3.2.Connect the unclogging device to the tubing connector. 2.2-1.3.3.Use a single-use syringe to aspirate 3ml CD80 wash solution, remove the needle and connect the syringe to the other end of the unclogging device. 2.2-1.3.4.Push the syringe plunger slowly until there comes liquid out of the sample probe tip. If no liquid comes out of the sample probe tip, insert a needle into the sample probe tip and push the syringe plunger.2.2-1.3.5.Leave the sample probe soaked with wash solution for about 10 minutes. Push and pull the syringe plunger for several times until liquid comes out of the probe tip evenly. 2.2-1.3.6.Use the syringe to aspirate deionized water and rinse the sample probe for at least 3 times. 2.2-1.3.7.Remove the unclogging device and the syringe, and then connect the tubing connector. 2.2-1.3.8.Remove the container.2.2-1 How to replace the washer2.2-2.1PurposeTo keep the sealingness of the fluidic path and sampling precision well2.2-2.2IntervalIf you remove and install the probe for about 2-3 times or it leaks between the probe’s fluid connector and the tubing connector, you should replace the washer with a new one. 92.2-2.3Procedures2.2-2.3.1 Follow the steps from 2.2.4.1-2.2.4.8 to remove the probe. You will see a small gasket inside the tubing connector which is removed from the probe.2.2-2.3.2 Remove the old washer with tweezers and put a new one inside the probe. Dispose the old one in proper way.The next step is installing the probe 2.2.4.9 Insert the probe back into the hole on probe arm, and align the hole on probe 2.2.4.10 plate to the rotor inside the arm. 2.2.4.11 Sleeve the spring on the rotor and screw the retaining screws to secure. 2.2.4.12 Pinch the probe by the part near the probe arm. Gently push the probe 2.2.4.13 upward and then release the probe to see if the spring can move freely. If yes, proceed to the next step. If not, check for errors and try again after removing the errors. 2.2.4.14 Connect the probe’ s circuit connector back to the circuit board2.2.4.15 Ensure the gasket is inside the probe2.2.4.16 Exercise caution when connecting the probe. Excessive force may bend the probe. Screw (clockwise) the probe’ s fluid connector back to the tubing connector.2.2.4.17 Add deionized water to a clean cup. Immerse the probe tip into the water by about 3mm and the LED on the circuit board will be lighted. Take the probe tip out of water, and the LED will be off. If the test succeeds, proceed to the next step.2.2.4.18 Check the marks inside the probe arm cover to see the orientation of the cover. Install the cover back to the probe arm.The marks inside the probe arm cover are shown in the figure below.102.2.4.19 Pull the probe arm to its highest point and rotate it to move the probe to a position above the wash well. 2.2.4.20 Load the sample/reagent disk.2.2.5 Verification Run the machine if no leakage around the connector,the replacement is OK.2.3 Replacing Syringe Plunger 2.3.1 Part Number 082-000731-00Syringe Plunger (500ul, zero dead volume)0040-10-32303Washer for Syringe2.3.2 Purpose For reliable aspiration 2.3.3 Interval Every year Every 100000 movements 2.3.4 Procedures 2.3.4.1 Place the Power to OFF2.3.4.2 Unscrew the screws on the syringe cover and remove the cover. The structure of the syringe is as shown in the figure below.112.3.4.3 Prepare a new plunger assembly (shown in the figure below) and soak the plunger tip in deionized water to eliminate bubbles2.3.4.4 Unscrew (counter-clockwise) the lower retaining screw. 2.3.4.5 Unscrew (counter-clockwise) the four retaining screws, remove the screws and space bars, and remove the syringe from the holder.2.3.4.6 Grab the Tee with one hand and the syringe connector with the other hand and unscrew (counter-clockwise) the syringe. Exercise caution so that the gasket on the syringe does not drop out and if it does, store it in a clean place for later installation.2.3.4.7 Unscrew (counter-clockwise) the plunger guide cap and pinch the plunger button to gently pull the plunger assembly from the syringe.2.3.4.8 Pinch the new plunger assembly by the plunger button and carefully insert the plunger tip into the syringe and push it all the way to the end. Screw (clockwise) the plunger guide cap until secure2.3.4.9 Immerse the syringe connector into deionized water. Pinch the plunger button, pull it to aspirate half syringe of deionized water and then push it to expel the deionized water and the air from the syringe. 12 [email protected] 2.3.4.10 Grab the Tee with one hand and the syringe connector with the other hand. Screw (clockwise) the syringe into the Tee until secure.2.3.4.11 Place the syringe on the holder. Install space bars and fix retaining screws. 2.3.4.12 Screw (clockwise) the lower retaining screw until secure. 2.3.4.13 Place the Power back to ON.2.3.5 Verification Enter the Alignment screen of the operating software and set the Vol. (R. Syringe) to 450ul. Click R. Syringe Aspirate. After the syringe finishes the motion, click R. Syringe Dispense. You may repeat this action several times. If there are not bubbles observed during the process and the alignment is correct,everyting is ok.2.4 Replacing Mixing Bar and Retaining Nut 2.4.1 Part Number BA31-20-41651, BA30-20-06774Mixing Bar, Retaining Nut2.4.2 Purpose For reliable testing results 2.4.3 Interval Every year 2.4.4 Procedures 2.4.4.1 Place the Power to OFF 2.4.4.2 Gently pull the bar arm to its highest point and move the bar to a position convenient to operate.2.4.4.3 Pinch the bar by the knurled part with one hand and unscrew (counter-clockwise) the retaining nut with the other hand until the mixing bar looses. Pull the bar downward to remove it and remove the nut.132.4.4.4 Align the new mixing bar to the bigger hole end of the retaining nut and gently screw it into the nut until the end of the bar is in line with the smaller hole end of the nut.2.4.4.5 Pinch the mixing bar by the knurled part and align the hole of the nut to the axis on the bar arm, then push the bar upward in the direction of the axis until it can’t proceed. Tighten the nut by screwing clockwise with the other hand.2.4.4.6 Ensure the bar is all the way pushed to the end. 2.4.5 Verification After replacing the bar, visually check whether the bar is vertical to the bar arm. If not, remove the bar and re-install it. If yes, proceed to the next step. 7 Pull the bar arm slightly and move the bar to a position above its wash well.2.5 Replacing Filter Assembly 2.5.1 Part Number BA31-30-56750Filter Assembly (2 Pcs, 1pkg)2.5.2 Purpose Keep reliable testing results 2.5.3 Interval 14Every 6 months 2.5.4 Procedures 2.5.4.1 Remove cap assembly from the DI water tank and place it on a clean desktop. Carefully remove the filter assembly from the cap assembly.2.5.4.2 Inject water into the new filter assembly through the big adapter by using the syringe. When water wells up from the small adapter, the injection is completed. Purpose: increase the weight of the filter assembly to make it sink to the bottom of the water tank.2.5.4.3 Connect the new filter assembly to the tubes of the cap assembly.2.5.5.4 Expel air from the filter assemby 15 [email protected] 1) Connect the DI water tank assembly to the analyzer (pay attention to the color of the adapters). Put the assembly into the water tank and make sure that the filter sink smoothly to the tank bottom and does not twist with the floater connecting rod. Tighten the cap of the DI water until secure. 2) Place the Main Power and Power of the analyzer to ON. Turn on the computer and start the operating software. 3) Reset 10 times (click Maintenance and then select Alignment, click Reset) to expel the air in the filter assemby and the tubes.2.5.5 Verification Check for large amount of buubles in the outlet tube. If yes, continue the resetting process; if not, the air expelling is completed. The installation is completed.2.6 Replacing Check Valve 2.6.1 Part Number M6Y-020003---Check Vavle2.6.2 Purpose To keep the sealingness of the fluidic path and unobstructed flow2.6.3 Interval Every 6 months 2.6.4 Procedures 2.6.4.1 Remove the rear panel and find the Check Vavle.16Check Vavle 2.6.4.2 Replace the Check Vavles with the new ones.2.6.5 Verification Run our analyzer and check if the liquid is weeping;If not,the replacement is OK.173.Chemistry Maintenance schedule BS-200 Maintenance ScheduleDI water tankN/AN/ABS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.Waste tankN/AN/ABS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.Inlet tubing of Cap assembly of DI Water TankN/AN/ABS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.Outlet tubing of Cap assembly of Waste TankN/AN/ABS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.Reagent/Sample diskN/AN/ABS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.Wash Wells of probe and mixing barN/AN/ABS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.Dust Proof NetN/AN/ABS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.Sample/Reagent Bar Code Reader WindowsN/AN/ACleaning Panels of Analyzing UnitN/AN/ABS-200 Chemistry Analyzer Operator’s Manual(V1.4) Chapter 5.Clean the Rotor of Reagent/Sample Probe/Mixer Drive AssemblyN/AN/AWipe the rotor with clean gauze.ISE daily cleaningN/AN/AISE pump calibrationN/AN/AITEMRelated PartQty12 MO NTWe ek ly Mo nth ly 6M on thsWHICHEVER COMES FIRSTBy CustomerEVERYBy EngineerHSC: Clean, R: Replace, A: Adjust, L: Lubricate, P: Perform, N: No action neededDa il yI: Inspect. Clean, Adjust or Replace if necessary.ISE Na electrodeN/AN/A10,000 tests or 6 monthsISE K electrodeN/AN/A10,000 tests or 6 monthsISE Cl electrodeN/AN/A10,000 tests or 6 monthsISE Li electrodeN/AN/A3,000 tests or 6 monthsISE Ref electrodeN/AN/A10,000 tests or 6 monthsLampBA30-10-06365Halogen Lamp(50W)1,000 hoursReagent/Sample probeBA40-30-61525Sample probeProbe washer0040-10-32307Washer for ProbeProbe unclog tool115-003182-00Probe Unclog ToolAcupuncture Needle0000-10-10916Acupuncture Needle10Syringe Plunger (500ul, zero dead volume)082-000731-00Syringe Plunger (500ul, zero dead volume)Washer for SyringeMixing Bar + Retaining NutSyringe washer Mixing Bar + Retaining Nut0040-10-32303 BA31-20-41651 + BA30-20-06774100,000 movementsDI water filter assemblyBA31-30-56750Filter Assembly (2 Pcs, 1pkg)Check ValveM6Y-020003---Check Valve18Reference